Sunday, December 13, 2009
Building Update 12/13/2009
›
Lots of activity is scheduled for this week. The ceramic tile is to begin on Tuesday as well as the plumber installing all of the fixtures. ...
Thursday, November 12, 2009
Building Update 11/12/09
›
Creative Sound and Lighting has been steadily working on the stage lighting and well as hanging the projectors. They have also begun install...
Thursday, November 5, 2009
Building Update 11/05/2009
›
The sprinkling system contractor (Brewer) has completed their work of adjusting the sprinker head to the ceiling grid and the ceramic tile i...
Monday, November 2, 2009
Building Update 11/02/2009
›
Ceramic Tile is being installed in the restrooms and the sprinkling system installer (Brewer) was draining down the system so that they can ...
Sunday, November 1, 2009
Updated Photos
›
Above is another photo of the Worship area, this time from the left side of the room. You can see where the screens are located on either s...
Building Update 11/01/2009
›
Sorry that I haven't been keeping everyone up to date on the building progress, but I've been under the weather this week. The park...
Saturday, October 17, 2009
Pictures
›
These are some additional pictures of the inside of the building. As you can see the ceiling grid has started and is almost complete.
Building Update 10/17/09
›
This image is in the foyer and the cross is located above the Welcome Center.
Wednesday, October 14, 2009
Building Update 10-14-2009
›
All of the exterior doors are now in place as well as the glass above the main entrance. The drop ceiling contractor is on site and has comp...
›