Building Update 10-14-2009

All of the exterior doors are now in place as well as the glass above the main entrance. The drop ceiling contractor is on site and has completed the grid along the hallway next to the loop and is starting the grid on the opposite hallway. Creative Sound and Lighting has completed the drops for the 2 video cameras and is now working on the stage lighting. It's been an exciting week. Hope to upload some new pictures later today.